Developer of proposed data center in Windsor Twp. outlines project incentives
WINDSOR TWP. - A data center proposed on nearly 200 acres of land at the corner of Pinch Highway and Lansing Road, southwest of Lake Interstate comes with financial incentives outlined in a "proposed community improvement agreement" attached to the site plan t
Illustrative imageWINDSOR TWP. - A data center proposed on nearly 200 acres of land at the corner of Pinch Highway and Lansing Road, southwest of Lake Interstate comes with financial incentives outlined in a "proposed community improvement agreement" attached to the site plan that was filed with Windsor Township on Nov. 13.
Applicant WT Project Owner LLC, a Delaware company, wants to build the facility on land at 6180 Nixon Road, west of Dimondale. The property is owned by Interstate Capital, a Birmingham, Michigan-based private equity firm that bought it last year.
The center would include two data center buildings of about 493,000 square feet each, generators, battery storage, a substation, a switchyard and other components, according to documents on the township website.
The site plan submission marks the fourth data center proposed in the Lansing area in the last year. The latest, from Colorado-based Lighthouse Sustainability, was for a more than $10 billion, 700 megawatt project along College Road in Delhi Township. The company abandoned its plans earlier this month after a public backlash.
Residents spoke out against the proposed Windsor Township project at a Nov. 18 township planning commission meeting.
Township officials have not scheduled a date to consider the proposal. A town hall meeting with the township board and the developer will be scheduled, according to the township's website. But a drafted "community improvement agreement" submitted by WT Project Owner LLC outlines incentives and promises linked to the center if it moves forward.
Here's a closer look at what the proposed agreement includes.
Developer would fund project escrow account
If the township planning commission approves a final site plan and the improvement agreement for the data center, the developer would fund an escrow account "in the amount of $500,000 (the "Project Escrow Account"), for use by the Township during the course of Project construction, as necessary and in good faith, for all Township consultant, review, permit, inspection and approval fees and/or legal expenses incurred by the Township regarding the Project, including with respect to approvals given for the Project, and/or enforcement of Township Ordinances regarding the Project."
If the funds in the account drop below $100,000, the developer would replenish the account to $500,000. Once the center is constructed the developer would maintain an escrow account of $50,000 to be "used by the Township to fund noise and water standard compliance monitoring and other Township costs for administrative oversight."
Developer would fund millions in 'trust'
The developer would fund a $13 million trust "to enhance the Township's ability to provide public services for the construction and operation of the Project." The township can use the money for "operations and government infrastructure in relation to the Project, including for Township facilities such as police and fire facilities and equipment and Township offices, so long as such expenditures are within the authority of the Township."
Funds for fire department promised
The developer would fund up to $2 million in fire trucks, training and equipment to the township's fire department "to enhance the ability of the Fire Department to serve the Project and other nearby lands."
READ MORE:
Nearby homeowners could seek compensation
The agreement provides for nearby homeowners with parcels of land outlined in the agreement, to be compensated by the developer for a loss in value due to the data center's construction.
"Developer will pay the Eligible Owner for that loss. This protection lasts for ten (10) years after construction of the Project begins (the "Protection Period"), and an Eligible Owner may be paid under it only once," according to the document.
Sound study would be paid for
The developer would pay an "independent professional sound consultant" to conduct a sound study to ensure the data center complies with the township's "sound requirements."
Center would not be expanded
According to the agreement, "The Project shall not be materially expanded beyond the approximate overall size depicted in the preliminary site plan..."
Facilities would be decommissioned after use
The developer will "demolish at its expense any building or structure constructed for the Project that is subsequently vacated and remains vacated and abandoned for a period of six (6) consecutive years...and will grade and seed with natural grasses the land on which the building or structure was located."
Conservation easement promised
The developer would preserve "25 acres of wetlands and woodlands" on the property by a conservation easement.
Center's water usage would be limited
The data center would use "a closed-loop cooling system for the equipment and not use a design that contains high-water-use evaporative cooling. Water use shall be generally limited to restrooms/domestic uses, humidity, landscaping, fire protection and general maintenance."
The center would connect to public water and sewer.
Contact Reporter Rachel Greco at [email protected]. Follow her on X @GrecoatLSJ.
This article originally appeared on Lansing State Journal: Developer of proposed data center in Windsor Twp. outlines project incentives